Aug launch for Artemis 1 moon rocket: NASA Report

text_fields
bookmark_border
Aug launch for Artemis 1 moon rocket: NASA Report
cancel

Washington: The launch of Artemis 1 moon rocket has once again been delayed according to NASA. The US space agency is planning to launch the rocket in August this year, according to media reports.

Artemis 1 was scheduled to be launched in late May 2022, but due to multiple delays in its final test, the wet dress rehearsal, the launch date had to be pushed further, with the new date likely to be in August.

NASA now plans to take its final test in June, and if all goes according to plan, it could set the stage for its first launch in August, Space.com reported.

The Artemis 1 stack, a huge Space Launch System (SLS) rocket with an Orion crew capsule on top, rolled out to Pad 39B at NASA's Kennedy Space Center (KSC) in Florida in mid-March for its "wet dress rehearsal", a crucial series of tests that includes fueling up the SLS.

IANS reports that although the wet dress began on April 1 and was supposed to wrap up two days later, the team encountered several problems, including a stuck valve on the mission's mobile launch tower and a hydrogen leak in one of the "umbilical" lines connecting the tower to the SLS. This led to delays and ultimately a halt after three fueling attempts.

On April 25, team members rolled the Artemis 1 stack off Pad 39B back to KSC's cavernous Vehicle Assembly Building (VAB) to investigate the problems and make the necessary fixes, NASA officials were quoted as saying last week, adding that the probe of the faulty valve continues.

However, even as the probe continues, the team remains optimistic for another wet dress try.

"We're looking right now at that next wet dress in the early to mid-June timeframe," Jim Free, associate administrator for the Exploration Systems Development Mission Directorate at NASA headquarters in Washington, was quoted as saying.

For this the teams would have to roll out the SLS and Orion from the VAB by late May because the Artemis 1 team needs 12 to 14 days to prepare for the wet dress test, Free added.

Free was confident that the fourth attempt would prove to be a success, but he acknowledged "it may take more than one attempt to get the procedures where we need them".

While NASA will not set a target launch date for Artemis 1 until the wet dress is complete, Free mentioned August as the likely earliest available time frame at this point.