Begin typing your search above and press return to search.
proflie-avatar
Login
exit_to_app
Trump
access_time 22 Nov 2024 2:47 PM GMT
election commmission
access_time 22 Nov 2024 4:02 AM GMT
Champions Trophy tournament
access_time 21 Nov 2024 5:00 AM GMT
The illness in health care
access_time 20 Nov 2024 5:00 AM GMT
The fire in Manipur should be put out
access_time 21 Nov 2024 9:19 AM GMT
America should also be isolated
access_time 18 Nov 2024 11:57 AM GMT
DEEP READ
Munambam Waqf issue decoded
access_time 16 Nov 2024 5:18 PM GMT
Ukraine
access_time 16 Aug 2023 5:46 AM GMT
Foreign espionage in the UK
access_time 22 Oct 2024 8:38 AM GMT
exit_to_app
Homechevron_rightBusinesschevron_right358 of 769 road...

358 of 769 road projects delayed; 1 rail project late by 276 months

text_fields
bookmark_border
358 of 769 road projects delayed; 1 rail project late by 276 months
cancel

New Delhi: A government report revealed that the road transport and highways sector is the top number of delayed projects while the railways and petroleum sector follow.

The former has 358 delayed projects from 769, while the latter two have 111 from 178 and 87 from 154 projects, respectively, PTI reported, citing the latest flash report on infrastructure projects for November 2022.

The report stated that the most delayed project is the Muneerabad-Mahaboobnagar rail project, which by 276 months. At second, the Udhampur-Srinagar-Baramulla rail project, which is late by 247 months. Belapur-Seawood-Urban Electrified Double Line is in the third position and is delayed by 228 months.

Further, it says that 756 projects are delayed with respect to their original schedules, and 304 projects have reported additional delays vis-a-vis their date of completion reported in the previous month.

Of the said 304 projects, 58 are mega projects, with expenditures of Rs 1,000 crore and above.

In the road transport and highways sector, the total original cost of implementation of 769 projects when sanctioned was ₹ 4,33,744.86 crore, but estimates ran later up to Rs 4,60,524.16 crore due to a cost overrun of 6.2 per cent. The expenditure incurred on these projects till November 2022 was ₹ 2,77,208.24 crore or 60.2 per cent of the anticipated cost of the projects.

In railways, the original cost of implementation of 173 projects when sanctioned was Rs 3,72,761.45 crore, which reached Rs 6,24,583.37 crore with a whopping 67.6 per cent cost overrun. The expenditure incurred on these projects till November was ₹ 3,59,996.26 crore, which is 57.6 per cent of the anticipated cost of the projects.

Regarding the petroleum sector, the total original cost of implementation of 154 projects was ₹ 3,81,885.12 crore. However, this was subsequently anticipated at ₹ 4,01,966.41 crore -- a cost overrun of 5.3 per cent. The expenditure incurred on these projects till November 2022 was ₹ 1,48,897.69 crore or 37 per cent of the anticipated cost of the projects.